Skip to content

HomeProjects

EnergyBAS-U and shutdown manager

Maintenance shutdown at Mölndal Energi

At Mölndal Energi's maintenance shutdown, WermKon coordinates health and safety management for around 100 people on site. Through daily presence, clear structure and continuous follow-up, we create the conditions for a safe and well-coordinated shutdown.

Client
Mölndal Energi
Sector
Energy
Our role
BAS-U and shutdown manager
Location
Mölndal
Period
Spring to autumn, recurring
On-site lead
Lena Jonsson
HSE consultant talking to a contractor on site

The assignment

How we ensure health and safety management during maintenance shutdowns at Mölndal Energi

During a maintenance shutdown, production at the combined heat and power plant is paused so that repairs, inspections and maintenance can be carried out. This means many contractors and tasks at the same time, in the same place. Around 100 people pass through the Mölndal Energi site during this period. The work runs from spring to autumn, and a complex plan has to work in practice. WermKon has been part of delivering the shutdown for several years.

The challenge

A complex shutdown requires clear coordination

A maintenance shutdown involves several parallel risks. For Mölndal Energi, these include work in confined spaces, many contractors and strict requirements to comply with the regulations of Arbetsmiljöverket, all under high time pressure. Arbetsmiljöverket is the Swedish workplace health and safety regulator, comparable to the UK's Health and Safety Executive (HSE).

Arbetsmiljöverket now treats larger maintenance shutdowns as building and civil engineering work, which means a BAS-U is required. A BAS-U is a Swedish construction-phase safety coordinator. WermKon's role is to make sure health and safety management works in practice. We are on site as both BAS-U and shutdown manager, and we are responsible for providing structure, a visible presence and follow-up throughout the shutdown.

The solution

Structure and follow-up every day

To bring structure to complex, time-pressured work, we work closely with the plant's operations, on site, every day. We hold daily coordination meetings with the contractors to make sure everyone has the same overview and knows who is doing what and when the work will be done.

At the same time, we carry out regular walk-rounds of the plant and weekly safety inspections to identify risks and non-conformities early. We also keep clear track of who is on site and which work is in progress, while maintaining an ongoing dialogue with both supervisors and tradespeople. Everything is documented and followed up continuously, so nothing falls through the cracks.

‘We have now worked with WermKon on several occasions and are very satisfied. They are highly competent, and their experience shows. We have had very good contact with the BAS-U who has been on site with us, and they have shown both a strong willingness to cooperate and real initiative. WermKon is a reliable and trustworthy partner to work with.’

Jonny SiwerstamMaintenance Manager, Mölndal Energi

The result

A safer site throughout the shutdown

Clear structure and daily presence give everyone working on site a shared overview of the work. This reduces the risk of misunderstandings, clashes between jobs and unsafe situations. Health and safety management becomes a natural part of daily work, not something that happens on the side. The result is better coordination, clearer responsibilities and a safer working environment throughout the maintenance shutdown.

We are on site every day while the work is carried out. We follow up, check in and act in time, so that risks do not turn into accidents.

Worth SEK 15,000Free of charge to you

Get a free needs assessment of your site.

We visit your workplace, review risks and working methods, and recommend the roles and skills you need on site.

Book a needs assessment

How it works

  1. 01You send us your details.
  2. 02We contact you and book a visit to your site.
  3. 03We review risks and working methods and recommend roles and skills.